April 27, 2023 - Roof, East wall, Electrical

Roof cement top layer complete and leveled
Back extension completed and a smooth leveling coat applied over all the roof.
There will be a final thin water proofing layer added and the "ends" of the roof overhangs
will be bricked and sealed to cover the metal beams before the roof tiles are installed.

East retaining wall in-progress
We're going with a two level step-down, rather than original three.
Another layer of blocks to be added to the nearest section before the header.

Normal ground slope is not really that high
The neighboring lot height is not nearly as high as it looks. Most of that is
excavated from my lot and the level will be returned to the original at some point.

The retaining wall will extend to the corner of the stairway
The ground level on my side of the retaining wall will also be quite a bit higher when filled
in.
After the drainage pipes to the register, etc. are in place. View is from bedroom window.

Channels for the electrical runs; Ceiling lights and wall switches
No easy drilling holes in wood studs or cutting into drywall.

Kitchen and Laundry 3-way switch clusters needs a couple pipes
All the piping channels will have metal mesh over them before the mortar is applied

Register for the laundry area in the back extension
There will be a small washtub nearest the door way then the washer and dryer.
Just thought I would show this since I forgot to take a picture of it a few weeks ago :-)
Picture Dates
- October 31, 2024 - Front Gate Installed
- October 17, 2024 - West Boundary Fence Installed
- October 10, 2024 - West Boundary Fence
- October 03, 2024 - Windows and Prep
- September 21, 2024 - Fencing the East Side
- September 12, 2024 - Catchup, Restart, and Secure the Border
- April 25, 2024 - Bathroom tile, Water System, Window Frames, Etc.
- April 04, 2024 - Garage Wall, Lower level and more
- March 07, 2024 - Bath, Ceiling, Windows & Doors
- February 22, 2024 - Bathroom, Primer and Lower Level
- February 8, 2024 - Decisions and a few minor things
- January 25, 2024 - Floors and More
- January 04, 2024 - BioDigester, More Inside Plaster & Cement
- December 28, 2023 - Garage Wall, Inside Plaster, Big Hole
- December 14 & 21, 2023 - Garage Wall, Plumbing
- December 06, 2023 - Rain Delay and Garage Wall
- November 30, 2023 - Plumbing Started & More Lower Level
- November 23, 2023 - More Lower Level & Front Garden
- November 09, 2023 - Lower Level & Front Garden Continues
- November 02, 2023 - Entrance, Lower Level & Front Garden
- October 26, 2023 - Even More Front Wall and Entrance
- October 4, 2023 - More Front Wall and Entrance
- September 21, 2023 - Front Wall and Entrance, Lower Level
- September 14, 2023 - Tower Walls, Prep for Entrance and Front Wall
- September 7, 2023 - Exterior Plaster, Lower Level
- August 24, 2023 - Even More Plaster, Bedroom Floor, Tower Wall
- August 17, 2023 - More Plaster, Lower Level Roof
- August 03, 2023 - Lower Level, House Inside Plaster, Front Views
- July 27, 2023 - Closet Plaster, Lower Level Roof
- July 20, 2023 - Lower Level, House Drains
- July 13, 2023 - Lot Corner, Cistern, House Drains
- July 6, 2023 - Cistern, Drainage, Miscellaneous
- May 31, 2023 - Cistern, Roof, Electrical
- May 11, 2023 - Roof, Retaining wall, Kitchen shelf
- April 27, 2023 - Roof, East wall, Electrical
- April 19, 2023 - More stuff done, More stuff to do
- April 13, 2023 - Roof, Registers, Workshop and East Wall
- April 05, 2023 - Ceiling, Roof and Workshop
- March 29, 2023 - Roof Prep, Workshop, Shower & Fire
- March 23, 2023 - Ceiling nearly finished, Lower Level Walls
- March 15, 2023 - More Ceiling, Walkway, Lower Level
- March 09, 2023 - Ceiling, Walkway, Lower Level
- March 01, 2023 - More Work on Ceiling, Stairs and Walkway
- February 23, 2023 - Work on Ceiling, Stairs and Walkway continues
- February 15, 2023 - Boveda ceiling started, Stairs and Walkway continue
- February 9, 2023 - Lower Structure, Entrance Stairs and Walkway
- January 25, 2023 - Lower Retaining Wall & Structure In-Progress
- January 5, 2023 - Roof Beams almost complete, Lower Level Retaining Wall
- December 15, 2022 - Ready for Roof Beams, Start Lower Level
- December 7, 2022 - Wall Headers and Peaks
- November 24, 2022 - Walls Getting Closer to Completion
- November 17, 2022 - Walls In-Progress ...continued
- November 9, 2022 - Foundation and Walls In-Progress
- October 27, 2022 - Starting to take shape, house build platform near completion
- October 13, 2022 - Work continues on the house build platform
- September 29, 2022 - Front retaining wall near completion
- September 15, 2022 - Back retention wall complete, side retention walls WIP
- September 8, 2022 - Back retention wall almost complete
- August 16, 2022 - Excavation complete; Back retention wall started
- August 3, 2022 - Excavation on-going
- July 28, 2022 - Excavation in-progress
Pictures are in a carousel. Use the arrows on left/right of the image to browse through them.
Latest pictures are loaded by default; older sets by clicking on the Picture Dates links above.