February 8, 2024 - Decisions and a few minor things

Slow week for large visible changes. Three rooms in the house to be finished before the rest will allow me to move in before the rest of the house is complete - the bedroom, bathroom, closet...plus the utility/storage room in the lower level and the fencing for the yard. They started the washing of the ceiling bricks and I have picked out a tentative paint color for the metal ceiling beams - pending a painted sample area.

Met with the guy that will be making the lower level windows and steel security doors for the utility/storage room. Decided to go with a submersible water pump for the cistern. Also finalized the placement of the main electrical box and internet connections.

Going to Guadalajara on Tuesday to visit a tile manufaturer's showroom. Need to select tiles for all the floors and wall tiles for the bath and laundry back-splash, etc.