September 12, 2024 - Catchup, Restart, and Secure the Border
Long-time since last update. Work has restarted; some minor interior work has been done, but now the focus is now on closing up the house and securing the border; windows, gates, walls and the fencing to come.
The previous herrero (blacksmith or metalsmith) disappeared on us for a couple months which pushed the schedule back and we had to find a new one.

Most of the wall tile, and floor tile, in place for the bathroom

Toilet, sink, etc. and final trim after water system installed

Bedroom closet, Floor tile and Window Installed

Bedroom "small" windows installed and being painted.
Large side wall window and floor tile still to go.

Living area window installed. Kitchen window not.
Kitchen window, large bedroom window, and front door will be done by the new herrero

Living area window view

House rear entrance windows installed.

Utility floor closed up, ready for water pump and filtration system

...and the windows frames, beams and ceiling have been painted

View of the house from the west side

Clean up of area and path for the west side fence

Some cement work for the gate from the garage area to the back

...and then the gate install
Also cement work along the wall to divert water in the rainy season (now)

Meter pole for electric, but cable still on the tree

Water cut-off notch inside front gate

Bio-digester septic system layout

Reduced number of step-levels on east wall
One level from gate to steps (was 3), one along side lower building (was 2),
one along main house
(was 2). It was for retaining wall levels, now levels for fence install

Prep for front wall security bar install

... and there they are

Main people gate install
Also clear outside the wall to allow apply of sealant and easier work on fence install.

Wide shot of the front
Eduardo Sr. checking the sealing of the front garden wall along the entrance.
Fill dirt will go above the sealant level for lawn or garden

Early days... prep for the rear section of the east wall
Looking from the back boundary wall

The rocks have been selected or busted up from the big ones
Looking from house rear retaining wall

Bringing it up to ground level from 40cm deep

Some in-place boulders were used as part of the wall
The rear wall is the association boundary wall in place since the 70's

Top view of east wall from the back boundary wall

View from the house rear entrance doorway
New portion of the wall to the left of the retaining walls corner.
This is a more recent photo after some "pointing" was done.

Looking up from "garden strip" behind the retaining wall

Looking down from "garden strip" behind the retaining wall
Picture Dates
- October 31, 2024 - Front Gate Installed
- October 17, 2024 - West Boundary Fence Installed
- October 10, 2024 - West Boundary Fence
- October 03, 2024 - Windows and Prep
- September 21, 2024 - Fencing the East Side
- September 12, 2024 - Catchup, Restart, and Secure the Border
- April 25, 2024 - Bathroom tile, Water System, Window Frames, Etc.
- April 04, 2024 - Garage Wall, Lower level and more
- March 07, 2024 - Bath, Ceiling, Windows & Doors
- February 22, 2024 - Bathroom, Primer and Lower Level
- February 8, 2024 - Decisions and a few minor things
- January 25, 2024 - Floors and More
- January 04, 2024 - BioDigester, More Inside Plaster & Cement
- December 28, 2023 - Garage Wall, Inside Plaster, Big Hole
- December 14 & 21, 2023 - Garage Wall, Plumbing
- December 06, 2023 - Rain Delay and Garage Wall
- November 30, 2023 - Plumbing Started & More Lower Level
- November 23, 2023 - More Lower Level & Front Garden
- November 09, 2023 - Lower Level & Front Garden Continues
- November 02, 2023 - Entrance, Lower Level & Front Garden
- October 26, 2023 - Even More Front Wall and Entrance
- October 4, 2023 - More Front Wall and Entrance
- September 21, 2023 - Front Wall and Entrance, Lower Level
- September 14, 2023 - Tower Walls, Prep for Entrance and Front Wall
- September 7, 2023 - Exterior Plaster, Lower Level
- August 24, 2023 - Even More Plaster, Bedroom Floor, Tower Wall
- August 17, 2023 - More Plaster, Lower Level Roof
- August 03, 2023 - Lower Level, House Inside Plaster, Front Views
- July 27, 2023 - Closet Plaster, Lower Level Roof
- July 20, 2023 - Lower Level, House Drains
- July 13, 2023 - Lot Corner, Cistern, House Drains
- July 6, 2023 - Cistern, Drainage, Miscellaneous
- May 31, 2023 - Cistern, Roof, Electrical
- May 11, 2023 - Roof, Retaining wall, Kitchen shelf
- April 27, 2023 - Roof, East wall, Electrical
- April 19, 2023 - More stuff done, More stuff to do
- April 13, 2023 - Roof, Registers, Workshop and East Wall
- April 05, 2023 - Ceiling, Roof and Workshop
- March 29, 2023 - Roof Prep, Workshop, Shower & Fire
- March 23, 2023 - Ceiling nearly finished, Lower Level Walls
- March 15, 2023 - More Ceiling, Walkway, Lower Level
- March 09, 2023 - Ceiling, Walkway, Lower Level
- March 01, 2023 - More Work on Ceiling, Stairs and Walkway
- February 23, 2023 - Work on Ceiling, Stairs and Walkway continues
- February 15, 2023 - Boveda ceiling started, Stairs and Walkway continue
- February 9, 2023 - Lower Structure, Entrance Stairs and Walkway
- January 25, 2023 - Lower Retaining Wall & Structure In-Progress
- January 5, 2023 - Roof Beams almost complete, Lower Level Retaining Wall
- December 15, 2022 - Ready for Roof Beams, Start Lower Level
- December 7, 2022 - Wall Headers and Peaks
- November 24, 2022 - Walls Getting Closer to Completion
- November 17, 2022 - Walls In-Progress ...continued
- November 9, 2022 - Foundation and Walls In-Progress
- October 27, 2022 - Starting to take shape, house build platform near completion
- October 13, 2022 - Work continues on the house build platform
- September 29, 2022 - Front retaining wall near completion
- September 15, 2022 - Back retention wall complete, side retention walls WIP
- September 8, 2022 - Back retention wall almost complete
- August 16, 2022 - Excavation complete; Back retention wall started
- August 3, 2022 - Excavation on-going
- July 28, 2022 - Excavation in-progress
Pictures are in a carousel. Use the arrows on left/right of the image to browse through them.
Latest pictures are loaded by default; older sets by clicking on the Picture Dates links above.